1) Rig movement diagram.
2) Sequence of installation of piles.
3) Information about the piles.
- Type of pile (working/test)
- Pile number
- Pile group number
- Grid location
- Pile diameter
- Diameter of cutting tool used.
- Specific gravity of bentonite slurry, with time of checking.
- Local ground level / Casing top level
- Length of permanent casing (liner) used.
- Date and time of starting boring
- Rate of penetration per meter
- Depth and reference number of sample taken intermittently during the boring activity.
- Date and time of completing boring
- Time of conducting penetration test & ‘N’ value recorded
- Pile bottom level
- Depth of pile as recorded by sounding
- Date and time of lowering reinforcement
- Top level of reinforcement cage
- Details of reinforcements
- Measurement of reinforcement
- Flushing start time
- Flushing finish time
- Concrete mix proportion & design strength
- Concrete slump
- Date and time of starting concreting
- Date and time of finishing concreting
- Pile top level
- Cut off level
- Total number of cubes taken
- Identification number of cubes taken
- Theoretical quantity of concrete required.
- Actual quantity of concrete used